Okay, so I have a NAPA sign installation to bid. 8' x 5'. This thing probably doesn't way more than 120lbs. (It was 170lbs including the crate)

Would you bother trying to anchor into I-beams with all thread + beam clamps? Or just bolt through the siding? I'm thinking the siding method is more than sufficient, but wanted to get a few opinions before I bid the job.

Thanks!
 

Attachments

  • 1764824273870.png
    1764824273870.png
    1.2 MB · Views: 133
  • 1764824422442.png
    1764824422442.png
    3.2 MB · Views: 131
  • 1764824465694.png
    1764824465694.png
    1.5 MB · Views: 130
Last edited:

tulsagraphics

New Member
FWIW: I say the word "bid" like I have competition. I don't - unless a company wants to drive an hour to beat me on price. lol
 
  • Agree
Reactions: 1 user

visual800

Active Member
just go thru the ribs and you will be just fine aint no sense in trying to hit those beams
 
  • Agree
Reactions: 3 users

JBurton

Signtologist
Use a dead man(2x4) to bridge the I beams, lag into the dead man. The sign could probably hang from 5-10 self tappers, but I'd prefer a more solid solution.
Are they going to move their trophy case before you come back for install?
 
  • Agree
Reactions: 2 users

Texas_Signmaker

Very Active Signmaker
The correct answer is to put a 2x4 like burton said.. short of that you could use winged anchors if it's light. You get any snow up there today?

1764898125040.png
 
  • Agree
Reactions: 2 users

tulsagraphics

New Member
Use a dead man(2x4) to bridge the I beams, lag into the dead man. The sign could probably hang from 5-10 self tappers, but I'd prefer a more solid solution.
Are they going to move their trophy case before you come back for install?
lol I hope so. Of course, I can always add that to the quote "clear space for the dead man: $500" :big laugh: -- actually you should see the rats nest on that "2nd floor". They must have been pack-ratting for 40-50 years
 
Last edited:

tulsagraphics

New Member
The correct answer is to put a 2x4 like burton said.. short of that you could use winged anchors if it's light. You get any snow up there today?

View attachment 180092
Howdy Tex! Snow was mostly southern OK, so we were in the clear. It's gettin' pretty chilly tho! I have yet to get in the air in "breezy" freezing temps. I hope to avoid as much of "that" as possible. #HumanPopsicle

The entire shipment weighed 170lbs., according to the shipping label (not my sign - something provided by corporate). Based on feel, it seems to be about 100-120lbs. No problem setting it on the material forks (just kidding! I didn't install forks. I swear it's just a "warranty joke"!) -- :rolleyes: -- and using a bunch of self tappers to hold it in place. Then I can run bolts through the wall and anchor a steel square tube behind the siding. Bridging columns sounds solid, but probably not an option here because the columns are so far apart. 15 to 20 feet -- maybe more. ** Edit -- maybe I could rig up a "45" dead man across the I beam and nearest column. I don't know. Maybe I'll just self tap / wing anchor this thing and see how it feels, then keep reinforcing using whatever method makes it feel extra solid.
 
Last edited:

monroesigns

Premium Subscriber
Verify if sealed architectural drawings are needed before submitting the bid. In many municipalities in Michigan, the ordinance required sealed drawings to secure a permit, and we work with the architect to establish the mounting method, which must be included on the drawing.

About 16 years ago, the building inspector required me to attend the inspection of an 8ft x 4ft ACM panel with cut vinyl letters. He asked me if I used 1.5" tap-cons - I said 2 inch. He said he would believe me and not require.me to take one out of the sign to show him. I have never been required to attend ANY other inspections.
 
  • Agree
Reactions: 1 users

JBurton

Signtologist
Edit -- maybe I could rig up a "45" dead man across the I beam and nearest column.
There ya go. Or run them vertically, I'd be willing to bet there is a horizontal piece just below the floor of that attic. Take a look at the screws on the outside of the building to find the steel.
Also, you can just use some decent lengths of 2x4's to act as a massive toggle bolt, spanning numerous connections of the ribbed panels to the steel.
Or you could do the work for a national that included a fabricated steel frame of 1.5"x.25" square tube, mounted to the horizontal girts every 8', with horizontal 3"x3"x.25" steel angle for actual mounting points. This is what we had to do for a mobile manufactured home plant, we kept joking that the building would be stripped of paneling and all the prefabbed homes would be vaporized during in an F5 tornado, but the sign and panels behind it would be nice and safe.
 
  • Agree
Reactions: 1 user

tulsagraphics

New Member
There ya go. Or run them vertically, I'd be willing to bet there is a horizontal piece just below the floor of that attic. Take a look at the screws on the outside of the building to find the steel.
Also, you can just use some decent lengths of 2x4's to act as a massive toggle bolt, spanning numerous connections of the ribbed panels to the steel.
Or you could do the work for a national that included a fabricated steel frame of 1.5"x.25" square tube, mounted to the horizontal girts every 8', with horizontal 3"x3"x.25" steel angle for actual mounting points. This is what we had to do for a mobile manufactured home plant, we kept joking that the building would be stripped of paneling and all the prefabbed homes would be vaporized during in an F5 tornado, but the sign and panels behind it would be nice and safe.
Good call. I think you're right. solid line of fasteners right below the proposed sign location. 1764990793685.png

And yeah, national sounds like overbuilding - and I'm generally a fan of that - within reason. Definitely a lot more work and $ though.
 

tulsagraphics

New Member
Verify if sealed architectural drawings are needed before submitting the bid. In many municipalities in Michigan, the ordinance required sealed drawings to secure a permit, and we work with the architect to establish the mounting method, which must be included on the drawing.

About 16 years ago, the building inspector required me to attend the inspection of an 8ft x 4ft ACM panel with cut vinyl letters. He asked me if I used 1.5" tap-cons - I said 2 inch. He said he would believe me and not require.me to take one out of the sign to show him. I have never been required to attend ANY other inspections.
Our town is very strict, but I "think" sealed architectural drawings mostly apply to pole signs above a certain height. Maybe it applies to wall mounted too? I just haven't had to deal with that yet -- guess we'll see what happens with the permit application.
Good thing is... since these signs are likely produced in bulk, I could just have the client reach out to corporate for a copy -- ideally. (although it might not be "that" straightforward -- the client should be sufficiently motivated to nag the piss out of them when he sees what it would cost for "us" to cobble together someone else's design and get an engineer to do his thing and stamp it)
 

JBurton

Signtologist
What's your plan for wiring? Biggest thing to know, if you're going to pull 120v through the wall into the cabinet, that wire needs to be in conduit/flex. If you are going to remote mount it, you could get away with jacketed wire or a grommet. Judging by all the crap up there, and the low height, I'd put it in the sign cabinet, otherwise you'll have to climb through that junk to mess with the power supplies. Is there a toggle switch on the cabinet or on a separate power supply box?
 

tulsagraphics

New Member
What's your plan for wiring? Biggest thing to know, if you're going to pull 120v through the wall into the cabinet, that wire needs to be in conduit/flex. If you are going to remote mount it, you could get away with jacketed wire or a grommet. Judging by all the crap up there, and the low height, I'd put it in the sign cabinet, otherwise you'll have to climb through that junk to mess with the power supplies. Is there a toggle switch on the cabinet or on a separate power supply box?
All good points, sir! For this job I'm only being requested to hang the sign -- I don't even have to touch the wiring. I think the owner has an electrician in the family.
 

tulsagraphics

New Member
Speaking of electrical -- not to hijack my own post, but kind of the same idea and/or possible loophole (excluding electrical details on a sign permit application). I've got some channel letters to produce for a store at a mall in Kansas. It's a tricky one (think: terrible font with recessed "claw marks" scratched through it, and also extending past the edges of the font). standoffs, backlit halo effect. I don't know of any trade suppliers willing to attempt this ridiculous thing. I'm only doing it (or attempting to) because it's for a friend (he won't budge on his trademarked logo).

I have a CNC now, and I'm willing to give it a shot using 1" PVC -- By the way, I just recently learned how heavy that stuff is. I feel bad I wasn't at my shop the day that poor delivery driver had to manhandle that thing into my garage o_O (I have keyless entry for deliveries).

Anyway, according to the mall lease agreement, all signs must be U.L. listed. Oof! So it got me thinking... electricians and/or lighting companies wire stuff up all the time. I don't see them carrying around U.L. stickers. So what if the lighting is "installed' (no visible wiring), but not hooked up? Does that get around the U.L. listing requirements? And then -- let's say a certified electrician were to "eventually" come by, inspect and actually hook it up... it would be his license / insurance that covers any liability. Maybe?
Surely I'm not the first person to think of this. I'm betting this "idea" will get shot down pretty quickly though.
 

Texas_Signmaker

Very Active Signmaker
Speaking of electrical -- not to hijack my own post, but kind of the same idea and/or possible loophole (excluding electrical details on a sign permit application). I've got some channel letters to produce for a store at a mall in Kansas. It's a tricky one (think: terrible font with recessed "claw marks" scratched through it, and also extending past the edges of the font). standoffs, backlit halo effect. I don't know of any trade suppliers willing to attempt this ridiculous thing. I'm only doing it (or attempting to) because it's for a friend (he won't budge on his trademarked logo).

I have a CNC now, and I'm willing to give it a shot using 1" PVC -- By the way, I just recently learned how heavy that stuff is. I feel bad I wasn't at my shop the day that poor delivery driver had to manhandle that thing into my garage o_O (I have keyless entry for deliveries).

Anyway, according to the mall lease agreement, all signs must be U.L. listed. Oof! So it got me thinking... electricians and/or lighting companies wire stuff up all the time. I don't see them carrying around U.L. stickers. So what if the lighting is "installed' (no visible wiring), but not hooked up? Does that get around the U.L. listing requirements? And then -- let's say a certified electrician were to "eventually" come by, inspect and actually hook it up... it would be his license / insurance that covers any liability. Maybe?
Surely I'm not the first person to think of this. I'm betting this "idea" will get shot down pretty quickly though.
The UL sticker has to be visible on the sign to pas inspection.
 
  • Agree
Reactions: 1 user

cwstevens

New Member
and the U.L. process is sooo cumbersome and expen$ive to be licensed and certified to label anything. The manufacturing company has to certify any product they ship out, it can't be done 3rd party upon reciept. it requires UL ratings for components, material data sheets, flammability ratings, VOC compliance, manufacture spec sheets, blah blah blah. The key here is whether AHJ (Authority Having Jurisdiction) far as "code enforcement" is concerned, it tends to be fairly lacking around here, chances are it will never be inspected by anyone from City of Tulsa... they have about a 6 year or more, backlog of signs we got permits for that they have never signed off on as being "inspected"...
 
  • Agree
Reactions: 1 user