Simply that.... 50% deposit required to initiate project/balance upon completion.
Now in your case, with 18 trucks, it’s a little trickier.
We just finished a job with almost 40 vehicles and it was a new customer, so we phrased it:
50% deposit to initiate project/balance per/as we go. We billed them a weekly invoice where the deposit was applied as we went… to what we finished that week. It’s kind of the same as if you’re doing a complete department store. As you finish a certain area, that area gets billed and paid. Explain that, at this size of an order, to keep their costs down, you’re billing them as you go. They can’t expect you to wait until you finish 18 trucks, unless you can do them all in two or three days.
Nice order if you get it… Good Luck.