• I want to thank all the members that have upgraded your accounts. I truly appreciate your support of the site monetarily. Supporting the site keeps this site up and running as a lot of work daily goes on behind the scenes. Click to Support Signs101 ...

Quoting multiple layouts on one job...?

Ken

New Member
Hi. I have a job to quote that involves 10 different layouts on a total of 26 signs. Most of it is on coro, but there are 3 aluminum sign faces in the quote. My question is :
Do you provide a quote that specifies the price for each " batch" of signs..or just a single price quote for the complete job?
Thanks...Ken
 

iSign

New Member
I'd probably lump design time into sign prices, but I'd show 9 signs at one price (noting that each sign has a unique layout, included in the price)

Then I'd show 17 more signs at a slightly lower price (noting the savings due to use of existing layouts)
 

Ken

New Member
Thanks for the input D.
I'll wait for a few more people to wake up and add to the thread.
BTW..it was cool to see some of your early posts on the 5 yr anniversary thread...
Quality replies back then , as they are now.
Cheers!
Ken
 
D

DARLAK

Guest
10 different layouts to me seems like 10 signs with some having multiples...

example:

3 coroplast 18 x 24's, file 1, @ $32 each
2 coro's 18x 24, file 2,@ $37 each

1 coro 18 x 24, file 3 @ $45 each

1 aluminum 18 x 24, file 3 @65 each

so on an so forth...

doing it this way takes just a few minutes more, but saves you if they come back and say, i changed my mind i need 4 of these or only 2 of these, if you clump them together it would be harder for the client to understand afterquote changes as opposed to laying them all out first hand....
 

Ian Stewart-Koster

Older Greyer Brushie
I'd recommunicate with the client & see what they really want, explaining that if they really need a multitude of prices & options, it'll take time to work out, which will add to the price of the job.

Many times when a request has come in like that, what you finally end up doing does not resemble the original request- so it takes some psychology to really work out what they're after, and price that for them- or get an anticiapetd budget from them first.

Alternately, show them existing work, completed, & tell them whatever you like, pricewise, verbally, for a similar one of five or ten of those, and a different price for three or six of these etc.

His reaction will tell you what he's really after, and you can tailor your direction that way.
 
Top