800 doors???

ep

New Member
I have a county bid to cut and apply vinyl numbers totaling 1.125 X 7.750 inches per door to over 800 doors. I'm new at this and tried using Estimate to price it, but it really doesn't take into account the labor. Any help in pricing this would really be appreciated.
 

Gino

Premium Subscriber
Welcome from PA.....................

Looks like you have some calculating ahead of you. Take your number there times 800 doors and figure out how much vinyl you will be buying… not to mention application tape. Next, figure in your weeding and taping time. Okay….figure how long it’s going to take you to do one door….. measuring, centering, applying, peeling off tape, removing guidelines and walking to the next door. Take that number times 800. Now figure in all your mistakes, mishaps, dropping things and bending over, people stopping you and asking you stupid questions and your breaks. Add that number into the equation. Next figure all the time you’ll be away from your shop missing customers calling on you and now going to another shop since you’re not there. Add up what your overhead is and plug that into the numbers. Don’t forget for the doors that go wrong and you have to go back to the shop and make replacements and then have to go back and re-do some of them. There is a lot of down time when you get into high numbers of repetitive things like this.



Good Luck................ and :Welcome:​
 

OldPaint

New Member
I have a county bid ...this is your 1st RED FLAG.... you do realize that dealing with municapalities....
you will work FROM YOUR MONEY....not theres????
they pay either every 2 weeks or monthly...do not pay UP FRONT DEPOSITS.....nor do they care when you need money.....BUT...they have 14 people who is gona tell you how this supposed to be done, code inforcement, and EPA..... will make sure youre in COMPLIANCE with them......factoring in all the other B.S. you need to add an AGRIVATION CHARGE....
 

cdiesel

New Member
Don't worry.. working with municipalities can be extremely profitable. Keep in mind that the cost of vinyl is an extremely small part of the equation, but it'll take you quite awhile to produce and apply these.

I'd be a peelin' and stickin' mofo!
Then again, I can usually get things straight on the first try without measuring.
 

Craig Sjoquist

New Member
find a die cutter now .. cause thats who will get bid in the end
your biggest consern would then be installation, cut a few out, install, and time that

git r dun
 

Farmboy

New Member
A quick guide for applying to that many doors might be a couple pieces of magnetic cut to varing lengths for different makes and models. Maybe line the top up with the window trim and the decal at the bottom. Just a thought, I have no idea if it would really work. :)
 

mtmdesigns

New Member
bid 9 dollars a unit and ack on 15 percent for mistakes. I can cut them and send them to you for $2400.
714-379-9245
 

Checkers

New Member
Don't spend more than 15 minutes on the bid. You will not win the bid if you expect to make money and try to produce them in-house. Die cutting is the only way to go. Use a vendor like Gregory1.com and add 40% profit to their price.
I would figure a few days on site for installation and add the appropriate amount for cleaning supplies and trip charge(s).

Checkers
 
like the others said watch municipalities. you'll probably have to file as a vendor(if your not already)& most have strict guidelines as far as insurance coverage you need to carry.But this can be a good learning experience just charge this as if it were the only job you were doing, not hope for future work(been there done that)& like shovelhead said make up an alignment tool for mounting to the doors. 1 person can tack them up & another can lay them out. could make qick work of that job. Good Luck----------Sean
 

Replicator

New Member
Welcome ep . . . Both Shovelhead and Gino have given you the best advice . . . Take it, It's FREE . . .

Although maybe ad the advice into the cost of your bid !
 

Pat Whatley

New Member
Assuming that they are all different numbers...
All in the same building or complex of buildings: $6.80 each
Scattered all over the county: add travel time based on shop rate

If you make a jig to keep them consistent layout time is virtually non-existent. We did an office building several years ago with 120-130 doors in it. It took two of us less than three hours...and being an employee at the time I promise you that I wasn't busting my butt to do them quickly. One person would go down a hall, clean and mark all the doors for installation with the jig. The other person would install the numbers and wipe off the stabilo line.

Take a couple of sheets of extra numbers 0-9 and just replace any you stretch or wrinkle as you go.

Costs: vinyl, tape, 22 hours labor (cut, weed, install) $1980
Selling cost: $5440
Profits: $3460 (and that's after paying yourself labor above)


All that said, if they're like the county here they're going to end up just buying the letters and installing them themselves so if you have to break it down in the quote make sure you price the letters high.
 

ep

New Member
800 Doors

Hi all THANK YOU very much for all of the advice. I am a one person shop and I need the experience so...I am going to bid $3.00 a piece. It will be either a good or bad learning experience, but at least it will be an experience.
 

Gino

Premium Subscriber
With your explanation of your situation and your being a one-man shop with little or no experience…. that is no reason to underbid a job. In fact, that is cruel and wrong to all the others that will be bidding on it that have proper insurance, proper installation techniques, using high end vinyl and quoting with overhead and profits figured into their bid.

If you bid that price of $3.00 each including installation…. I invite you to be honest with your customer and tell them that you aren’t experienced, aren’t sure of what you’re doing and basing your quote solely on getting experience. Give your customer the right and decent information, so they can make an informed decision. Heck, you have to live here and to screw with your own local government; just to get a job because you think you can make some money is totally wrong.

This has nothing to do with the attitude…. ‘you have to start somewhere…. ‘ This has to do with being honest and upfront with your customer and being competent in representing yourself and the trade as a whole.

Your statement….. It will be either a good or bad learning experience, but at least it will be an experience. is a piss poor way to go into anything….. especially your own bread and butter.


Hello sir, I need 800 fence posts installed on my land to keep my stock in.

Okay, we can handle that.... I'll go to Home Depot and get 4' posts and drive them in with a heavy hammer and I'll have it finished in a few days.

A week later and your arm is falling off you hand the guy the bill and he says I need the rails too, where are they ??

Oh, that will be extra.

No, I have your proposal and also there's only three foot sticking out of the ground, my horses will jump over that. You told me four foot. Written right here. They need to be taller.

Oh why oh why... didn't I know to get all the information and learn how to do this better before I tackled this job ??
 

iSign

New Member
I assume they are mostly sequential numbers, and the County probably has them in some digital form, which would be worth getting from them, even though it's probably going to be M$ word, publisher or XL. Some programs like Omega have features to quickly set-up sequential numbering, but I'm would allow for at least 2 hours to typeset, print or email for approval (on complex jobs, I always get the client involved in approving things prior to production) and set up for cutting.

If printing 3 across on a 24" roll, with a weed border around each, you'll have 267 rows, or about 13 yards of vinyl (80 sq. ft.)

If it's a basic block lettter, and you have a quality plotter, with properly set blade depth and pressure I'd guess around 3 or 4 hours labor to weed and tape. (cutting time not included)

So far, that 5 or 6 hours, plus cutting time & material cost is worth at least $800 to me.

Installation fees would require knowing more details. If all doors are in one or two building, and I can work early, late or on weekends (when less people are passing through, and making the usual "it's spelled wrong", or "it's crooked" comments that no one ever thought of before) then I'd expect to easily do 40 in an hour... 20 hours total (I think it could be as fast as 10-12 hours, so I wouldn't mention time estimates to the client)

Anyway, I'd want $2000 for the install, plus the $800 above... I don't think ep's quote is bad at all.

I know my rates are $100 an hour & other parts of the country can afford to offer much lowe shop rates. Of course I'd be more careful going over my numbers if this was a bid I was really submitting... but on the surface, ep's $2400 is not that bad IMO.
 